Street Repair Schedule for Agoura Hills This Week

The city is undertaking some pavement rehabilitation and application of slurry seal work for the next four weeks.

From the city of Agoura Hills:

The city is undertaking some pavement rehabilitation and application of slurry seal work for the next four weeks at various locations throughout the city. The hours of operations will be approximately from 7 a.m. to 4 p.m., Monday-Friday. The streets affected are: 

• Roadside Drive
• Lewis Road from Roadside Drive
• Rainbow View Drive 
• Rainbow Hill Road
• Larboard Lane
• Reyes Adobe Road
• Slurry seal and striping of the Recreation Center parking lot at 30610 Thousand Oaks Boulevard
• Slurry seal and striping of the Park-N-Ride lots north and south of the 101 freeway and Kanan Road

Schedule for this week of July 14-18 is as follows:

Tuesday, July 15, 2014
The contractor will be continuing with the construction of the rolled curb and pavement on west side Lewis Road and Agoura Road.

Wednesday, July 16, 2014 
The contractor will be continuing with the construction of the rolled curb and pavement on west side Lewis Road and Agoura Road, and will be lowering manhole and water valve covers through the streets under this project.

Thursday, July 17, 2014 
The contractor will be doing the first coat of striping on all the parking lots, and we hope to be able to open the parking lots to the public a few hours after the paint is installed.

Friday, July 18, 2014 
The contractor will be finishing up with the installation of the rolled curb and pavement on west side Lewis Road and Agoura Road.

Please Note: The contractor will be setting up traffic control in all areas and the street will be reduced to only one driving lane while work is taking place. Please use caution while driving through these areas.

This is an ongoing schedule and will be updated at the end of the week.